Project Timeline

The plan for the new EACC website: seven pages, two rounds of review, one week of development. Live on 2 December.

Duration
6weeks
Pages
7incl. home
Client reviews
2rounds
Launch
02.122026

Key dates and milestones

DateStepTypeStatus
Wed 28 OctWeek 1

Updated homepage

The reworked homepage with refined visuals, copy and the finalised map.

Presentation In progress
29 – 30 OctThu – Fri

Homepage feedback

EACC shares one round of consolidated feedback.

EACC Upcoming
2 – 10 NovMon – Tue

Remaining pages

Services, Customers, Tech, Team, Blog and Blog article, designed in the approved direction.

Design Upcoming
Wed 11 NovWeek 3

All pages presented

The full website, all seven pages, shared for review.

Presentation Upcoming
12 – 13 NovThu – Fri

Website feedback

EACC shares one round of consolidated feedback on all pages.

EACC Upcoming
16 – 18 NovMon – Wed

Revisions

Final changes across all pages.

Design Upcoming
Fri 20 NovWeek 4

Design approval

EACC signs off the final design, and development begins.

Sign-off Upcoming
23 – 27 NovMon – Fri

Development

The approved design is built, including the interactive map and blog.

Build Upcoming
30 Nov – 1 DecMon – Tue

Testing and fixes

Checks across browsers and devices before going live.

Build Upcoming
Wed 2 DecWeek 6

Launch

The new EACC website goes live.

Live Upcoming

Seven pages.

Round 1 · 28 Oct Round 2 · 11 Nov

Home

28 Oct

Services

11 Nov

Customers

11 Nov

Tech

11 Nov

Team

11 Nov

Blog

11 Nov

Blog article

11 Nov